Contract No: NAR-EPC-03001
Contract Type: EPC
Client: Central Oil-Producing Regions
Kick Off: November 2024
Initial Contract Duration: 12 Months
Project Status: Ongoing
Location: Nar, Bushehr
Scope of Work
Project Specifications
Rearrangement of the Nar Field Gas Booster Station
Including:
1- Design and rearrangement of the Nar Gas Booster Station to suit the new compressors in order to resolve the gas pressure drop problem.
2- Procurement and supply of all equipment required in the rearrangement plan.
3- Implementation, pre-commissioning and commissioning of the entire station and updating all software and hardware of the new gas turbocompressor system control and all equipment required by the plan.